11.06.26
Moses Lake
Data center equipment yard (North) foundations
11.06.26
Moses Lake
Data center structural steel installation
11.06.26
Moses Lake
Admin building loading dock foundations
10.29.26
Moses Lake
Data center building structural steel erection
10.28.26
Moses Lake
Underground utilities progressing for data center infrastructure
10.21.26
Moses Lake
Foundation grade beams and electrical conduit duct bank form and concrete pour
10.09.26
Moses Lake
Spread footings concrete pour via pump truck
10.08.26
Moses Lake
Data Center building West structural beam
09.29.26
Moses Lake
Electrical duct bank conduit placement and stub up for equipment
09.26.26
Moses Lake
Foundation grade beams and electrical conduit duct bank form and concrete pour
09.22.26
Moses Lake
Pouring the foundation at Moses Lake
09.16.26
Moses Lake
Piping installation at Moses Lake
09.14.26
Moses Lake
Pre-delivery inspections at Vertiv's factory
09.09.26
Moses Lake
Signed an agreement with PowerSecure to deliver backup power at Moses Lake
08.07.26
Moses Lake
Backup generation inspections for Moses Lake
08.06.26
Sharon
Transformer delivery and installation in Sharon
04.27.26
Moses Lake
Decommissioned BTC mining and demolished building in Moses Lake
10.23.26
Moses Lake
Structural spread footings being set
10.23.26
Moses Lake
Site civil utility at generator yard
11.06.26
Moses Lake
Data center equipment yard (North) foundations
11.06.26
Moses Lake
Data center structural steel installation
11.06.26
Moses Lake
Admin building loading dock foundations
10.29.26
Moses Lake
Data center building structural steel erection
10.28.26
Moses Lake
Underground utilities progressing for data center infrastructure
10.21.26
Moses Lake
Foundation grade beams and electrical conduit duct bank form and concrete pour
10.09.26
Moses Lake
Spread footings concrete pour via pump truck
10.08.26
Moses Lake
Data Center building West structural beam
09.29.26
Moses Lake
Electrical duct bank conduit placement and stub up for equipment
09.26.26
Moses Lake
Foundation grade beams and electrical conduit duct bank form and concrete pour
09.22.26
Moses Lake
Pouring the foundation at Moses Lake
09.16.26
Moses Lake
Piping installation at Moses Lake
09.14.26
Moses Lake
Pre-delivery inspections at Vertiv's factory
09.09.26
Moses Lake
Signed an agreement with PowerSecure to deliver backup power at Moses Lake
08.07.26
Moses Lake
Backup generation inspections for Moses Lake
08.06.26
Sharon
Transformer delivery and installation in Sharon
04.27.26
Moses Lake
Decommissioned BTC mining and demolished building in Moses Lake
10.23.26
Moses Lake
Structural spread footings being set
10.23.26
Moses Lake
Site civil utility at generator yard
11.06.26
Moses Lake
Data center equipment yard (North) foundations
11.06.26
Moses Lake
Data center structural steel installation
11.06.26
Moses Lake
Admin building loading dock foundations
10.29.26
Moses Lake
Data center building structural steel erection
10.28.26
Moses Lake
Underground utilities progressing for data center infrastructure
10.21.26
Moses Lake
Foundation grade beams and electrical conduit duct bank form and concrete pour
10.09.26
Moses Lake
Spread footings concrete pour via pump truck
10.08.26
Moses Lake
Data Center building West structural beam
09.29.26
Moses Lake
Electrical duct bank conduit placement and stub up for equipment
09.26.26
Moses Lake
Foundation grade beams and electrical conduit duct bank form and concrete pour
09.22.26
Moses Lake
Pouring the foundation at Moses Lake
09.16.26
Moses Lake
Piping installation at Moses Lake
09.14.26
Moses Lake
Pre-delivery inspections at Vertiv's factory
09.09.26
Moses Lake
Signed an agreement with PowerSecure to deliver backup power at Moses Lake
08.07.26
Moses Lake
Backup generation inspections for Moses Lake
08.06.26
Sharon
Transformer delivery and installation in Sharon
04.27.26
Moses Lake
Decommissioned BTC mining and demolished building in Moses Lake
10.23.26
Moses Lake
Structural spread footings being set
10.23.26
Moses Lake
Site civil utility at generator yard